Joint Use Licensing Process

Application

A prospective licensee is required to make its application via the National Joint Utilities Notification System to PNM.

To apply via NJUNS:

  • Go to NJUNS.com and log into the pole attachment module
  • Enter attachment information
  • Sumbit maps
  • Submit payment for application - Apply online (njuns.com)

Application review and inspections

  • PNM performs field survey and inspection - To be completed by PNM within 45 days of receipt of application
  • Make-ready report sent to applicant for consideration
  • If applicant accepts, based on make-ready report and contract, the work is performed - If no make-ready work is required, applicant/licensee installs attachment after receiving approval - If make-ready work is required, PNM completes make-ready work and applicant/licensee then installs attachment and submits final as-built maps
  • PNM performs final inspection