Cell Site Checklist - pnmprod
Joint Use Cell
Site Check List
Items requested from cell site licensee during application process:
- completed contact sheet
- contract exhibits (whichever applies): - "Exhibit A" Āæ facilities lease - "Exhibit B" Āæ pole attachment application
- application fee
- NJUNS's pole attachment submittal to PNM
- site walk invitation
- structural analysis on PNM transmission / distribution structures
- Drawings (items reviewed by PNM to include): - company name - clearances - general configuration - structural attachment - PE review stamp - location: structure number and address - conduit number and placement - electric service source and PNM NSD representative - ground equipment layout and square footage requirements - fence, gates, door references - easements - reference to IEEE Standard 487 (Grounding Requirements in High Voltage Situations) - Qwest Standard 77321 (Verification of Sufficient Isolation Requirements) - RF data
- upon completion of project, as-built drawings submitted to PNM (electronic version)
Services provided to cell site licensee from PNM during application process:
- Engineering review of drawing submittals to ensure lessee designs attachments in a professional and technically acceptable manner; PNM's review does not in any way constitute approval of engineering design. Lessee is totally responsible for design.
- preparation of zoning letter to governing authority
- access coordination of proposed cell site locations, including*: - transmission structure access for structural analysis information acquisition - substation access for environmental reviews and/or other information gathering
-
National Joint Utilities Notification ID and assistance with initial application submittal to PNM
*Additional fee required since locations require PNM journeyman remain present at site